Hazardous nuclear fuel removal begins at Fukushima

Operator of Japanese power plant takes first steps in long process of decommissioning

Workers wearing protective suits and masks are seen during operations to remove fuel rods from a spent fuel pool inside the No.4 reactor building at Fukushima nuclear power plant . Photograph:Tokyo Electric Power Co/Handout via Reuters
Workers wearing protective suits and masks are seen during operations to remove fuel rods from a spent fuel pool inside the No.4 reactor building at Fukushima nuclear power plant . Photograph:Tokyo Electric Power Co/Handout via Reuters

The operator of Japan's wrecked Fukushima nuclear plant took the first step today in the long and hazardous process of decommissioning the facility, extracting four fuel rods from their container for later removal.

Tokyo Electric Power Co, known as Tepco, said it transferred the rods to a steel cask within the same cooling pool in a badly damaged reactor building, beginning the delicate and unprecedented task of removing 400 tonnes of highly irradiated spent fuel from that reactor.

“We will continue with the work from tomorrow and proceed, paying close attention to safety,” Tepco said in a statement.

While battling leaks of radiation-contaminated water around the plant, which was knocked out by Japan’s mammoth March 2011 earthquake and tsunami, Tepco has embarked on decommissioning four reactors at the Fukushima Daiichi plant. That task is likely to take decades and cost tens of billions of dollars.

READ SOME MORE

The company must carefully pluck more than 1,500 brittle and potentially damaged assemblies from the unstable reactor No. 4. Tepco estimates that removing all the rods from the reactor will take a year, although some experts say that is an ambitious target.

The cask holds 22 rods. Transferring this first batch will take about two days and it will take about a week to get the cask to the common storage pool in another building, a Tepco spokesman said.

Moving them is urgent because they are being stored 18 metres above ground level in a building that has buckled and tilted and could collapse if another quake strikes.

Removing the rods have been likened to taking cigarettes out of a crushed pack.

If the rods are exposed to air or if they break, huge amounts of radioactive gases could be released into the atmosphere. There are 50-70 in each of the assemblies, which weigh around 300 kg and are 4.5 metres long.

Reuters