A project to turn an old work depot into tea rooms at a park in one of the country’s wealthiest suburbs ended up costing almost 25 per cent more than budgeted.
Dublin City Council said the final bill for the conversion work at Palmerston Park, located next to some of the most expensive houses in the city, was almost €683,000.
The original contract amount for the project in Dartry was €556,000 but unforeseen extra costs arose after work began.
Dublin City Council said two existing floor slabs had to be broken out while the foundations for existing external walls were not strong enough and needed underpinning.
‘Bloodied but not bowed’: Connemara’s Misunderstood Heron food truck announces sudden closure
Leaving Cert student killed after car entered river in Co Tipperary named
Catriona Carey and brother Jack Carey sent forward for trial on company law charges
Protest held as US judge arrested and charged with obstructing immigration operation
The local authority said there were other problems with the walls and that work on additional kerbs, drainage and site clearance also took place.
It said some savings were made by reducing the scale of a gravel area beside the new tea rooms and a reduction in the number of parasols provided.
An information note said: “Other design changes to items like lighting fittings, metalwork (tapping rails), security (protection cages) and external entrance mats have also been implemented.
“Finally, significant additional soft landscaping works have been added to the works.”
The council said that the conversion of the depot at the historic park included a dining area, a serving area, storerooms, toilets and other facilities.
It said that “unforeseen existing building structural issues” had added around €30,000 to the bill and only became evident when work began.
A note said: “These included the very unusual situation where the walls were built on top of the floor slab, which then had to be cut back, the walls underpinned and additional supports to the foundations.
“It said the work also meant the initial plan to insulate the building would not work and that a more expensive option was chosen instead.
The building achieved a A3 Ber rating from B1 Ber rating preconstruction ... “[what this] means is lower fuel costs and significantly less CO2 emissions,” the council said.
It said landscape works had accounted for an extra €80,000 in costs with only a basic level provided for in the original pricing.
Their information note said: “The increase in cost included for a full planting scheme plus twelve months maintenance in and around the tea rooms, drainage, Wicklow granite kerbing and associated works.
“[This] was justified given the historic nature of the park and the need to use quality materials.”
The council said miscellaneous extra costs accounted for €17,000 while there were delay claim accounts of around €6,000.
Asked about the project, Dublin City Council said it had nothing further to add.